1. Introduction

A detailed schedule will be issued for the current and upcoming release. Planning for a release runs approximately over a time frame of 3 months.
Once development has started, a new schedule is made with stakeholders for the next release.

2. Planning

3. IPROTECT: Release 10.4

Jan2023FebMarAprMayJunJulAugSepOctNovStart of 10.4iProtect GOLD release
10.3
Nieuwe strook
10.4 Simons Voss
OS. based

Dom support in iProtect Mobile access

Minimize impact: iProtect update

iProtect functionality: On/Off

Testing 10.4

Bug fixing / maintenance

O.S. Security

iProtect Security

Minimize impact: iProtect update

Meta data / Postgresql

Fairplay

Maintenance SV-VCN

Support of PIN code keypads ( Simons & Voss - Wireless online)

Support 802.1x server

DOM support in iProtect Mobile Access

3.1 Details release 10.4

Priority

Description

Type

Short description

Ticket

Time estimate

FAT date *

SAT date *

Project leader

Notes

1

DOM support in iProtect Mobile Access

strategic

Sales

PBS-268 - Getting issue details... STATUS

2

Minimize impact: iProtect update (Local database Pluto)

strategic

iProtect CLOUD

ACT-1999 - Getting issue details... STATUS

3

iProtect functionality: On/Off

strategic

ACT-2445 - Getting issue details... STATUS

3wk

4

DORMA KABA (OSS)

5

Support 802.1x on Server

Customer

PI

AP-157 - Getting issue details... STATUS

2wkn

6

?

SimonsVoss Maintenance

Maintenance

Ticket and issues will be reviewed. Not all tickets will be solved because of the time.

ACT-1145 - Getting issue details... STATUS

3wk

7

1

Support of PIN code keypads ( Simons & Voss - Wireless online)

Customer

Windmill park TKH Germany

ACT-3463 - Getting issue details... STATUS

august 2023

Marcel van Kersbergen

8

Fairplay Certus / 20face

strategic

4wkn

Peter vd Brink

9

Meta data

strategic

Preparation for PostgreSQL

ACT-2124

  • Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT) are collectively referred to as commissioning. It is part of the Good Engineering Practices.

1

Priority

Description

Type

Short description

Ticket

Time estimation

FAT date *

SAT date *

Project leader

Notes

Priority

2

Pluto: Support ACaaS (“VPN”)

?

?

Details: DOM support in iProtect Mobile Access

Jan2023FebMarAprMayJunJulAugSepOctNovDecPilot releaseiProtect GOLD releaseFirst releaseClosing release
10.4

Fix existing OSS (DORMA KABA / SV / DOM OSS)

Testing 10.4

Bug fixing / maintenance

O.S. Security

iProtect Security

Sent invitation to mobile through iProtect

Access when presenting a mobile device on an offline lock throught Cosmos Access

Access when presenting a mobile device on a Sirius iX through Cosmos Access

Support DOM lock event upstream through Cosmos Access and iProtect

Support DOM RF/NM

Meeting DOM

Architectural design

Support DOM lock event upstream through Cosmos Access and iProtect

Password management

Backup Bridge

Linking a lock to bridge

Linking a lock to a door

Scheduled tokens

Multi Node support

Reorganize events

Support DOM RF/NM

Configure RF NM in iProtect (Link readers)

Reader state (Automatic/Open/Closed)

Pulse reader

Reorganize events

Battery management (events / status)

Multi site code support

1

Short description

Estimated time line

Finished

2

Support DOM online cylinder and door handles through iProtect

 

Target date: 1-04-2022

 

 

  •  
3

Sent invitation to mobile through iProtect

  •  
4

Access when presenting a mobile device on an offline lock throught Cosmos Access

  •  
5

Access when presenting a mobile device on a Sirius iX through Cosmos Access

  •  
6

Multiple Node support

  •  
7

Password management

  •  
8

Backup Bridge

  •  
9

Linking a lock to a bridge

  •  
10

Linking a lock to a door

  •  
11

Support DOM RF/NM

ACT-3073 - Getting issue details... STATUS

  •  
12

Configure RF NM in iProtect (Link readers)

  •  
13

Reader state (Automatic/Open/Closed)

ACT-3617 - Getting issue details... STATUS

  •  
14

Pulse reader

ACT-3616 - Getting issue details... STATUS

  •  
15

Fix existing OSS (Dorma Kaba, DOM OSS, Assa Abloy,)

  •  
16

Reorganize events

  •  
17

Scheduled tokens

In progress

  •  
18

Support DOM lock event upstream through Cosmos Access and iProtect

BB-1674 - Getting issue details... STATUS

  •  
19

Battery management (events / status)

ACT-3639 - Getting issue details... STATUS

  •  
20

Multi site code support

ACT-3706 - Getting issue details... STATUS

  •  
21

  •  

4. iProtect 10.5

Priority

Description

Type

Short description

Ticket

Time estimation

FAT date *

SAT date *

Project leader

Notes

1

1

Single sign-on

Strategic

PI

PBS-116 - Getting issue details... STATUS

1m + 2m

April 2023

December 2023

Needed: a functional description @Mark knops

2

1

Implementation - Support biometrics

Strategic

ICC / Eurojust

PBS-212 - Getting issue details... STATUS

4wkn

Q1 2024

Which hardware/reader are we going to support? Prices?

3

1

Deister improvements

Customer

PI

ACT-3471 - Getting issue details... STATUS

2wkn

4

1

UTC time

Strategic

Preparation for PostgreSQL

ACT-164 - Getting issue details... STATUS

4wkn

5

1

Integration of pagerservices

Customer

PI

?

June 2023

Q1 2024

Mark Knops

PI Zwolle: Minimaal de volgende gegevens dienen vanuit het toegangscontrolesysteem te worden opgehaald: naam; personeelsnummer; functie; afdeling

6

Support of Tatile Vega BASIC MK2 (STARK platform)

Customer

C&C partners

ACT-3464 - Getting issue details... STATUS

Leszek Schmidt

7

ANSSI certificering

Strategic

France

  • Factory Acceptance Testing (

FAT) and Site Acceptance Testing (SAT) are collectively referred to as commissioning. It is part of the Good Engineering Practices.

4.1 Other parts, Not iProtect related

1

Priority

Description

Type

Short description

Ticket

Time estimation

FAT date *

SAT date *

Project leader

Notes

Priority

2

Reader manager: Empty biometric container PHG to re-use the card

CC

1wk

Needed: a functional description (@Sander Zonnveld)

3

Reader manager: Security update

SR

Secure communication with the reader

4

OSDP t=cl support

SR

3.1 Details release 10.6 (2024)

1

Priority

Description

Type

Short description

Ticket

Time estimation

FAT date *

SAT date *

Project leader

Notes

Priority

2

CUSTOMER

Customers would like an export regarding the access rights, but then seen from the reader/door.

Customer

NS

ACT-3349 - Getting issue details... STATUS

Mark Sloot

3

CUSTOMER

Export (CSV) possibility: Hardware overview per line

Customer

NS

ACT-3348 - Getting issue details... STATUS

Mark Sloot

4

User login of the TANlock should be changed after iProtect has started the communication with the TANlock

Maintenance

Security

ACT-2623 - Getting issue details... STATUS

TANlock will implement this end Sept. 2023

5

We should be able to use more card technologies with TANlock

Customer

Sales request

ACT-2625 - Getting issue details... STATUS

TANlock will implement this end Sept. 2023

6

Simplify the line dialog

Maintenance

ACT-3127 - Getting issue details... STATUS

7

Update jasper reports (deprecation)

Maintenance

Security

ACT-1465 - Getting issue details... STATUS

8

No logout button in maintenance page

Maintenance

Security

ACT-1599 - Getting issue details... STATUS

9

Img, video and canvas (deprecation)

Maintenance

Security

ACT-2645 - Getting issue details... STATUS

10

Use a One Time Password (OTP) for the Java service

Maintenance

Security

ACT-3514 - Getting issue details... STATUS

11

Hide Technical passwords

Maintenance

Security

ACT-3507 - Getting issue details... STATUS

12

CUSTOMER

Standardize Reporting / External event service

Customer

General

ACT-2654 - Getting issue details... STATUS

2wkn

Ziggo, NS

5To be definied

1

TrakaWeb, keyfob management

2

Card enrollment in iProtect

3

?

iProtect: Online (repository) update

SR

6. Too complex for current environment

Due to the complexity and lead time of the project, the wishes below will not be implemented.

Description

Short description

Customer

Ticket

Status

Project leader / Sales contact

Date

1

7. Long term roadmap

Ticket

iProtect to new environment (Postgres)

Ziggo, NS, Pro-rail, Politie, Hospital DE https://www.postgresql.org/

New controller line (Pluto / Orion)

DOM: Locker functionality

License structure

Logical and Physical Acces?

Support of Docker container (IPROTECT CLOUD)

TKH Germany, NS, https://www.oracle.com/nl/cloud/cloud-native/container-registry/what-is-docker/

New controller line : Cloud support

Generic TKH reporting mechanism

iX card reader OSDP t=cl support

Reader manager as a Library

  • No labels